Civil construction site with reinforcement and lifting equipment.
our approach

TCD – Cloud Break CV010

TCD required survey support for final trim and grading of earthworks for a 7 km long conveyor with 9 culverts for stormwater drainage.
Project Overview

Survey expertise in practice.

TCD required survey support for final trim and grading of earthworks for a 7 km long conveyor with 9 culverts for stormwater drainage.

DELIVERY

Our role on the project.

  • Culhig provided machine control and guidance for graders and excavators including updating design models and continuous quality checks.
  • Final survey reports carried out with total station for maximum accuracy with 25 mm tolerance.
  • Survey control and set-out for 9 large culverts crossing the conveyor.
  • Aerial surveys carried out of handover surfaces from mining to calculate additional quantities required outside of scope.
  • Concrete footings and construction of tunnel for conveyor to run under mining haul road.
OUTCOME

Delivery that makes a difference.

  • The work was completed without incident and within budget.
  • Significant remeasure quantities were calculated from mining’s handover surface which presented TCD with additional scope and claims.
  • Survey and construction of tunnel carried out ahead of schedule allowing mining haul road to be reopened earlier than planned.

Similar projects

Christmas Creek – Vertical WHIMS Facility Upgrade – Bulk Earthworks

Christmas Creek – Vertical WHIMS Facility Upgrade – Bulk Earthworks

Engineering & Construction Surveying

As-Constructed Surveys

View project

TCD – Solomon Queens Conveyor

TCD – Solomon Queens Conveyor

Engineering & Construction Surveying

Survey Control Networks

Monitoring

3D Laser Scanning & Reality Capture

View project