Christmas Creek – Vertical WHIMS Facility Upgrade – Bulk Earthworks
Culhig Surveying were engaged by TCD to provide machine guidance and engineering survey support on the construction of the WHIMS (Wet High Intensity Magnetic Separation) Facility at FMG Christmas Creek Mine Site.
Project Overview
Survey expertise in practice.
Culhig Surveying were engaged by TCD to provide machine guidance and engineering survey support on the construction of the WHIMS (Wet High Intensity Magnetic Separation) Facility at FMG Christmas Creek Mine Site.
DELIVERY
Our role on the project.
- Construction of the WHIMS Building Pad, Concentrate Thickener Pad, belt Filter Pad, Screen Building Pad, two Switch room Pads and crane pads.
- Construction and modification of 10,000m³ access roads around the perimeter of the Vertical WHIMS Facility.
- Construction and modification of various drainage systems, including the supply and installation of culverts and open drains.
- Control establishment.
- Civil scope verification surveys.
- All clearing permit drafting and set out for the client (as required).
- Set out for trenching and services.
- Bulk earthwork model preparation.
- Machine guidance management.
- Test location pick ups.
- Volumes surveys for periodic claims.
- Drafting for handover.
OUTCOME
Delivery that makes a difference.
- The work was completed without incident.