our approach
Covalent Lithium – Mount Holland Mine
Survey support for mine development, village construction and associated infrastructure at Mount Holland.
Project Overview
Survey expertise in practice.
Covalent Lithium’s Mount Holland mine is situated 100 km south of Southern Cross in the Shire of Yilgarn. The mine and concentrator are located on a brownfield area that was previously the Bounty Gold Operation. Through their projects at the Mount Holland mine and concentrator and the Kwinana refinery, Covalent Lithium will be producing battery quality lithium hydroxide. The project includes the commissioning of the mine, concentrator, camp, roads and general infrastructure. Culhig Surveying provided Covalent Lithium with surveying support teams on an ad hoc and full-time basis from November 2019 to December 2021.
DELIVERY
Our role on the project.
- Culhig Surveying assisted with all aspects of the mine start-up, including but not limited to drill collar pickups, camp and road construction, control establishment, process and non-process infrastructure, existing infrastructure surveys, clearing management and included.
- Set out for original camp.
- Set out for new village phase I and II.
- Bulk earthworks for new village. (Removal of unsuitable material) provide volumes.
- Prepare machine guidance files for grader.
- Screw piles for village units.
- Underground services set out and as-constructed.
- Wastewater plant, spray field and access road set out.
- Mine and Village access roads.
- Telstra tower pad design and set out.
- Western Power pylon, power line heights above MAR and Village access roads.
- Core yard and road set out & infrastructure.
- Saline pond layout.
- Staked out various GDP and tracked clearing.
- Vegetation avoidance.
- Data Processing.
OUTCOME
Delivery that makes a difference.
- The work was completed without incident.
- The Client expressed their genuine satisfaction with our service throughout the project start up.