Due to increased demand, GD Pork sought to develop a number of existing pork-producing facilities it ran within WA.
Project Overview
Survey expertise in practice.
Due to increased demand, GD Pork sought to develop a number of existing pork-producing facilities it ran within WA. Kojonup was one such development.
DELIVERY
Our role on the project.
- Complete topographical survey of the Kojonup facility.
- Develop earthworks package for stage 1 and stage 2, (cut to fill, imported fill, roads etc).
- Develop sewer alignment proposal, inclusive of grade, reduced levels and sumps required.
- Develop feed overland conveyor alignment proposal (alignments, grade, longitudinal sections etc).
- Establish primary control network for construction and expansion stages.
- Complete all set out as required for civil scope stage 1 (14 new warehousing facilities).
- Complete all set out for conveyor systems.
- Provide on-site support as required throughout planning and construction phases.
OUTCOME
Delivery that makes a difference.
- The work was completed without incident.
- Scope was delivered on time and on budget.