our approach
Dalgaranga Gold Mine – Process Plant
Engineering surveying and dimensional checks supporting SMP installations at the Dalgaranga process plant.
Project Overview
Survey expertise in practice.
On 6 August 2012 Gascoyne acquired an 80% interest in the advanced Dalgaranga gold project and surrounding exploration tenements from private tenement holders. The Dalgaranga project is located approximately 70 km by road NW of Mt Magnet in the Murchison gold mining region of Western Australia and covers the majority of the Dalgaranga greenstone belt.
DELIVERY
Our role on the project.
- Provide competent engineering surveyor to oversee the SMP installations.
- Specialist sub mm Sag Mill installation.
- Complete all primary control establishment to be used for the duration of the construction period.
- All clearing permit drafting and set out for the client.
- Set out for trenching and services.
- Auditing Pre-pour check on 360m³ mill slab foundation.
- Verticality checks on critical items.
- Head and Tail pulley alignments.
- Set out of all services.
- As-built survey of all services.
- Drafting for handover.
OUTCOME
Delivery that makes a difference.
- The work was completed without incident.
- Scope was delivered on time and on budget.