Survey control, set-out and as-built documentation for the Dalgaranga camp and its associated services.
Project Overview

Survey expertise in practice.

On 6 August 2012 Gascoyne acquired an 80% interest in the advanced Dalgaranga gold project and surrounding exploration tenements from private tenement holders. The Dalgaranga project is located approximately 70 km by road NW of Mt Magnet in the Murchison gold mining region of Western Australia and covers the majority of the Dalgaranga greenstone belt.

DELIVERY

Our role on the project.

  • Provide competent mine and engineering surveyor to oversee the 250-man camp design and construction.
  • All initial camp control establishment to be used for the duration of the construction.
  • All clearing permit drafting and set out for the client.
  • Building layout proposals.
  • Service layout proposals.
  • Design assistance for footpaths and services.
  • Set out of all services.
  • As-built survey of all services.
  • Drafting for handover.
OUTCOME

Delivery that makes a difference.

  • The work was completed without incident.
  • Scope was delivered on time and on budget.

Similar projects

Christmas Creek – Vertical WHIMS Facility Upgrade – Bulk Earthworks

Christmas Creek – Vertical WHIMS Facility Upgrade – Bulk Earthworks

Engineering & Construction Surveying

As-Constructed Surveys

View project

TCD – Solomon Queens Conveyor

TCD – Solomon Queens Conveyor

Engineering & Construction Surveying

Survey Control Networks

Monitoring

3D Laser Scanning & Reality Capture

View project